  With all testing completed, the new sanitary sewer system servicing Burkettsville and New Weston is up and running. Project Manager Jared Ebbing, Fanning Howey Associates, says residents can tie in at any time. The first bills will go out to residents in January whether or not they are in the system. The sewer project was completed in September, ahead of schedule, and came in about $300,000 less than estimated.